commercial projects

The Village UMC
• Location: Wintergreen Rd. West of I-35
• Project Status: 
Utility installation complete, paving ongoing, project 70% complete (12/19)
   
                          Storm sewer connections being finalized, project 90% complete (1/20)
                             Inlet boxes being finalized and working on Punch-list, project 95% complete (2/20)
• Projected Completion Pending  
    
Desoto House of Peace Community Center
• Location: Belt Line in front of Summit Parks
• Project Status: 
Ongoing paving work and finalizing storm sewer connection, project 60% complete (12/19)
  
                           Fire Lane work ongoing, project 80% complete (1/20)
                             Fire Lane work complete, Approach waiting to be poured, project 95% complete (2/20)
• Structure Status: TBD
• Projected Completion Fall 2018
     
DeSoto Nursing and Rehabilitation Center 
• Location: South-West corner of Hampton Rd. and Centre Park Blvd.
• Project Status: 
Awaiting Pre-Construction Meeting (12/19)
                             Awaiting Pre-Construction Meeting (1/20)
                             Awaiting Pre-Construction Meeting (2/20)
• Structure Status: TBD
• Projected Completion TBD

Athlos - Desoto K-8 Charter School 
• Location: South-East corner of Cockrell Hill Rd. and Wintergreen Rd.
• Project Status: 
Design Review of Traffic plan (12/19)
                             Design Review of Traffic plan (1/20)
                             Design Review of Traffic plan (2/20)
• Structure Status: TBD
• Projected Completion TBD
   
Holiday Inn & Suites Hotel
• Location: I-35 Frontage Rd. between The Meadows Pkwy and Wintergreen Rd.
• Project Status: 
Awaiting pre-construction meeting (12/19)
                             Awaiting pre-construction meeting (1/20)
                             Awaiting pre-construction meeting (1/20)
• Structure Status: TBD
• Projected Completion: TBD

Fuzzy's Taco Shop
• Location:
228 Pleasant Run Rd.
• Project Status:
 
Utilities being installed, project 50% complete (12/19)
  
                           Utilities complete, project 85% complete  (1/20)
                             Pavement for drive and parking poured, working on sidewalk project 95% complete  (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Mark at DeSoto Apartment Complex
• Location:
South-east corner of Belt Line Rd. and Westmoreland Rd.
• Project Status: 
Grading work on-going (12/19)
                             Utility work started, project 35% complete (1/20)
                             Utility work ongoing, project 45% complete (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Hampton Retail Center
• Location:
1713 N. Hampton Rd.
• Project Status: 
Awaiting Pre-con. (12/19)
                             Awaiting Pre-con. (1/20)
                             Awaiting Pre-con. (2/20)
• Structure Status: TBD
• Projected Completion: TBD
 
DeSoto Transitional Care Center
• Location:
108 Barrows Pl.
• Project Status: 
Paving started 25% complete, Project 40% Complete (12/19)
                             Paving complete, retaining wall along creek being designed, Project 85% Complete (1/20)
                             Retaining wall along creek design being finalized, Project 95% Complete (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Southfield Park 35 - Building No. 5
• Location:
South-east corner of Old Hickory and Danieldale Rd.
• Project Status: 
Design Review (12/19)
                             Design Review (1/20)
                             Design Review (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Shops at Wintergreen
• Location:
South-east corner of Wintergreen Rd. and Cockrell Hill Rd.
• Project Status: Site grading ongoing (12/19)
                             Site grading ongoing (1/20)
                             Utility work started, building pad complete (2/20)
• Structure Status: TBD
• Projected Completion: TBD
 
Mechanic Shop
• Location:
1365 Lyndon Ave.
• Project Status: Pending
• Structure Status: TBD
• Projected Completion: TBD
 
DeSoto Professional Park Road
• Location:
West side of Bolton Boone Dr. north of Danieldale Rd.
• Project Status: Design Review (12/19)
                             Design Review (1/20)
                             Design Review (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Parc at Daniel Farms - Apartment Complex Phase I
• Location:
West side of Bolton Boone Dr. north of Danieldale Rd.
• Project Status: Design Review (12/19)
                             Design Review (1/20)
                             Design Review (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Golden Rule Charter School
• Location:
Wintergreen Rd.
• Project Status: Site Grading work started (12/19)
                             Utilities being Installed, project 35% complete (1/20)
                             Utilities work ongoing, Fire Lane being prepped for install, project 40% complete (1/20)
• Structure Status: TBD
• Projected Completion: Fall 2020
 
Penny Paws Addition
• Location:
North-West corner of Belt Line Rd. and Westmoreland Rd.
• Project Status: Design Review (12/19)
                             Design Review (1/20)
                             Project Accepted for Construction (2/20)
• Structure Status: TBD
• Projected Completion: TBD

STAYAPT Suites (Hotel)
• Location:
South-West corner of Centre Park Blvd. and I-35 Frontage Rd.
• Project Status: Design Review (2/20)
• Structure Status: TBD
• Projected Completion: TBD

Jubilee Community Church
• Location:
108 N. Lyndalyn Ave.
• Project Status: Design Review (2/20)
• Structure Status: TBD
• Projected Completion: TBD