commercial projects

Comfort Suites Hotel
• Location: Wintergreen Rd. West of I-35
• Project Status: 
Project 98% complete awaiting final (10/18)
                             Project 98% complete awaiting final (11/18)
                             Project 98% complete awaiting final (12/18)
                             Project 99% complete awaiting final (1/19)
                             Project 99% complete awaiting final (2/19)
                             Project 99% complete awaiting final (3/19)
• Projected Completion Fall 2018

  
The Village UMC

• Location: Wintergreen Rd. West of I-35
• Project Status:  
Awaiting pending Pre-Construction Meeting Documents (10/18)
                             Pre-construction meeting complete (11/18)
                             Pre-construction meeting complete (12/18)
                             Pre-construction meeting complete (1/19)
                             Contractor prepping site to begin Construction (2/19)
                             Contractor prepping site to begin Construction (3/19)
• Projected Completion Pending  
   
 
Best Western - GLO Hotel
• Location: I-35 Frontage Rd. between The Meadows Pkwy and Southpointe Dr.
• Project Status: Complete, awaiting As-builts for final release (10/18) 
                             Complete, awaiting As-builts for final release (11/18)
                             Complete, awaiting As-builts for final release (12/18) 
                             Awaiting As-builts for final release (1/19)
                             Awaiting As-builts for final release (2/19)
                             Awaiting As-builts for final release (3/19) 

• Structure Status: Complete (10/18)  

• Projected Completion Summer 2018

Desoto House of Peace Community Center
• Location: Belt Line in front of Summit Parks
• Project Status: 
Construction 50% complete, utility work ongoing (10/18)
                             Construction 50% complete, paving work started (11/18)
                             Construction 50% complete, paving work started (12/18)
                             Construction 50% complete, paving work started (1/19)
                             Construction 55% complete, paving work started (2/19)
                             Construction 85% complete, finalizing utility connections (3/19)
• Structure Status: TBD
• Projected Completion Fall 2018
    
 
Grocery Store - Lot 1, Block A 
• Location: North-West corner of belt Line Rd. and Westmoreland Rd.
• Project Status: 
Awaiting Pre-Construction Meeting (10/18)
                             Awaiting Pre-Construction Meeting (11/18)
                             Awaiting Pre-Construction Meeting (12/18)
                             Awaiting Pre-Construction Meeting (1/19)
                             Awaiting Pre-Construction Meeting (2/19)
                             Awaiting Pre-Construction Meeting (3/19)
• Structure Status: TBD
• Projected Completion TBD

DeSoto Nursing and Rehabilitation Center 
• Location: South-West corner of Hampton Rd. and Centre Park Blvd.
• Project Status: 
Awaiting Pre-Construction Meeting (10/18)
                             Awaiting Pre-Construction Meeting (11/18)
                             Awaiting Pre-Construction Meeting (12/18)
                             Awaiting Pre-Construction Meeting (1/19)
                             Awaiting Pre-Construction Meeting (2/19)
                             Awaiting Pre-Construction Meeting (3/19)
• Structure Status: TBD
• Projected Completion TBD

Athlos - Desoto K-8 Charter School 
• Location: South-East corner of Cockrell Hill Rd. and Wintergreen Rd.
• Project Status: 
Design Review of Traffic plan (10/18)
                             Design Review of Traffic plan (11/18)
                             Design Review of Traffic plan (12/18)
                             Design Review of Traffic plan (1/19)
                             Design Review of Traffic plan (2/19)
                             Design Review of Traffic plan (3/19)
• Structure Status: TBD
• Projected Completion TBD
 
 
Access Storage
• Location: South-East corner of Hampton Rd. and Danieldale Rd.
• Project Status: 
Construction 60% complete, utility work started (10/18)
                             Construction 65% complete, utility work completed (11/18)
                             Construction 65% complete, utility work completed (12/18)
                             Construction 70% complete, utility work completed (1/19)
                             Construction 70% complete, utility work completed (2/19)
                             Construction 80% complete (3/19)
• Structure Status: TBD
• Projected Completion TBD

La Quinta Inn & Suites
• Location: I-35 Frontage Rd. and Centre Park Blvd.
• Project Status: 
Awaiting Pre-Construction Meeting Documents (10/18)
                             Awaiting Pre-Construction Meeting Documents (11/18)
                             Awaiting Pre-Construction Meeting Documents (12/18)
                             Awaiting Pre-Construction Meeting Documents (1/19)
                             Awaiting Pre-Construction Meeting Documents (2/19)
                             Awaiting Pre-Construction Meeting Documents (3/19)
• Structure Status: TBD
• Projected Completion TBD

E.R. Carpenter LP EPS Plant
• Location: South-West corner of Talon Dr. and Peregrine Way
• Project Status: 
Working on Tilt-up walls 25% Complete (10/18)
                             Working on Tilt-up walls 75% Complete (11/18)
                             Working on paving, Tilt-up walls Complete (12/18)
                             Working on paving, Project 80% Complete (1/19)
                             Working on paving, Project 80% Complete (2/18)
                             Working on punch-list, Project 99% Complete (3/18)
• Structure Status: TBD
• Projected Completion TBD

VCA Animal Clinic
• Location: 201 N. Lyndalyn Ave.
• Project Status: 
Cleared to start construction (10/18)
                             Utility work 50% complete (11/18)
                             Utility work 50% complete, paving on-hold per Building Inspections Dept. (12/18)
                             Utility work 50% complete, paving on-hold per Building Inspections Dept. (1/19)
                             Utility work 50% complete, paving on-hold per Building Inspections Dept. (2/19)
                             Utility work 80% complete, paving started (3/19)
• Structure Status: TBD
• Projected Completion TBD

Holiday Inn & Suites Hotel
• Location: I-35 Frontage Rd. between The Meadows Pkwy and Wintergreen Rd.
• Project Status: 
Design Review (10/18)
                             Plans accepted for construction, awaiting pre-construction meeting (11/18)
                             Plans accepted for construction, awaiting pre-construction meeting (12/18)
                             Awaiting pre-construction meeting (1/19)
                             Awaiting pre-construction meeting (2/19)
                             Awaiting pre-construction meeting (3/19)
• Structure Status: TBD
• Projected Completion: TBD

Fuzzy's Taco Shop
• Location:
228 Pleasant Run Rd.
• Project Status: 
Awaiting Pre-construction Meeting (10/18)
                             Awaiting Pre-construction Meeting (11/18)
                             Awaiting Pre-construction Meeting (12/18)
                             Awaiting pre-construction meeting (1/19)
                             Awaiting pre-construction meeting (2/19)
                             Waiting on Building Inspections to release to start construction (3/19)
• Structure Status: TBD
• Projected Completion: TBD

Mark at DeSoto Apartment Complex
• Location:
South-east corner of Belt Line Rd. and Westmoreland Rd.
• Project Status: 
Design Review (10/18)
                             Design Review (11/18)
                             Design Review (12/18)
                             Design Review (1/19)
                             Design Review (2/19)
                             Planned Development Amendment through Planning and Zoning (3/19)
• Structure Status: TBD
• Projected Completion: TBD

Hampton Retail Center
• Location:
1713 N. Hampton Rd.
• Project Status: 
Design Review (10/18)
                             Design Review (11/18)
                             Design Review (12/18)
                             Design Review (1/19)
                             Design Review (2/19)
                             Accepted for Construction, Awaiting Pre-con. (3/19)
• Structure Status: TBD
• Projected Completion: TBD
 
DeSoto Transitional Care Center
• Location:
108 Barrows Pl.
• Project Status: 
Design Review (10/18)
                             Plans accepted for construction, dirt work ongoing and awaiting pre-construction meeting (11/18)
                             Site Grading started (12/18)
                             Site Grading ongoing (1/19)
                             Stormwater system installed, Project 10% Complete (2/19)
                             Utilities installed, Project 25% Complete (3/19)
• Structure Status: TBD
• Projected Completion: TBD

Southfield Park 35 - Building No. 5
• Location:
South-east corner of Old Hickory and Danieldale Rd.
• Project Status: 
Design Review (10/18)
                             Design Review (11/18)
                             Design Review (12/18)
                             Design Review (1/19)
                             Design Review (2/19)
                             Design Review (3/19)
• Structure Status: TBD
• Projected Completion: TBD

Shops at Wintergreen
• Location:
South-east corner of Wintergreen Rd. and Cockrell Hill Rd.
• Project Status: Design Review (2/19)
                             Design Review (3/19)
• Structure Status: TBD
• Projected Completion: TBD