Subdivisions

The Homestead at Daniel Farm - Phase 1A 
68 lots – Residential
Project Status: Utilities complete, 90% complete (5/19)
                           Utilities complete, Paving 40% complete (6/19)
                           Paving complete, working on Punchlist (7/19)
Developer: Wildwood Development Company I, L.P.

Engineer: Dietz Engineering
Contractor: Wildwood Development Company I, L.P.

Summit Parks Phase 2 
72 lots – Residential
Project Status: Utility installation ongoing, completing storm drain work, project 90% complete (5/19)
                          Utility installation complete, Paving 55% complete (6/19)
                          Paving complete, Finishing detention pond and Punchlist items ongoing (7/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: Alluvium Development
 
Hidden Lakes Phase 1 
40 lots – Residential
Project Status:  Design Review (5/19)
                           Design Review (6/19)
                           Design Review (7/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: TBD

Hidden Lakes Phase 2 
31 lots – Residential
Project Status:  Design Review Complete, Preliminary plat process ongoing (5/19)
                           Awaiting Pre-Con meeting, Preliminary plat process ongoing (6/19)
                           Awaiting Pre-Con meeting, Preliminary plat process ongoing (7/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: TBD

Cole Crossing Estates 
66 lots – Residential
Project Status: Grading work ongoing, Project 10% complete (5/19)
                          Utilities being installed 80% complete (6/19)
                          Utilities complete, storm sewer system being installed project 45% complete (7/19)
Developer: Harlan Properties

Engineer: Land Design
Contractor: TBD

Trees Farm Phase I 
101 lots – Residential
Project Status: Paving to start awaiting weather conditions project 55% complete (5/19)
                          Utilities installed, paving to start, project 50% complete (4/19)
                          Paving to start awaiting weather conditions project 55% complete (5/19)
Developer: Bloomfield Homes, LLP

Engineer: Engineering Concepts & Design, LLP
Contractor: Precision Management and Construction

 
Ten Mile Creek Estates  
89 lots – Residential
Project Status: Design Review (5/19)
                          Design Review (6/19)
                          Design Review (7/19) 
Developer: Harlan Properties, Inc.
Engineer: LandDesign
Contractor: TBD
 
Parkerville Meadows Phase 3
 
112 lots – Residential
Project Status: Pre-con meeting held.(5/19)
                          Started utility work and storm drain work 10% complete (6/19)
                          Utility work ongoing as well as storm drain work ongoing 40% complete, started grading site (7/19)
Developer: Kapsen Development Group, LLC

Engineer: Atlas Associates, Inc.
Contractor: TBD

Hampton Meadows Phase 2-B 
44 lots – Residential
Project Status: Awaiting Pre-con. (5/19)
                           Site Grading and retaining wall on southside started (6/19)
                           Grading ongoing and utilities being installed, 10% complete (7/19)
Developer: LGI Homes, LLC

Engineer: Pape-Dawson
Contractor: TBD

Summit Parks Phase 3 
58 lots – Residential
Project Status: Design Review (5/19)
                           Design Review (6/19)
                           Awaiting Pre-construction meeting (7/19)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: Alluvium Development

Kentsdale Farm Phase 4 
54 lots – Residential
Project Status: Design Review (5/19)
                           Design Review (6/19)
Developer: Wildwood Development Company

Engineer: Engineering Concepts & Design, L.P. 
Contractor: TBD

Christarm WinWIn Addition
5 lots – Residential
Project Status: Design Review (5/19)
                           Design Review (6/19)
Developer: Christarm Custom Homes, LLC

Engineer: OKM ENGINEERING, INC.
Contractor: TBD