Future Projects

Chattey Rd. - Pleasant Run Rd. to Belt Line Rd. Improvements
Engineer: EJES, Inc.
Contractor: TBD
Project: Chattey Road is an existing two-lane asphalt roadway located within a residential community. The improved roadway will be a 27’ undivided concrete roadway with curb and gutter, closed drainage, sidewalks, retaining walls, sewer line crossings, water line replacement, landscaping and lighting.
Project Status: 
Contractor Execution ongoing (12/18)
                             Contractor Execution ongoing (1/19)
                             Contractor Execution ongoing (2/19)
                             Awaiting Atmos Energy to relocate gas line (3/19)
                             Awaiting Atmos Energy to relocate gas line (4/19)
                             Awaiting Atmos Energy to relocate gas line (5/19)
Construction anticipated to begin Spring 2019
   
Pleasant Run Rd. - Joint MCIP Project # 1- Dallas County
Engineer: Garver
Contractor: TBD
• Project:  Pleasant Run Rd. (Westmoreland Rd. – Cockrell Hill Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: 
Preliminary design ongoing (12/18)
                             Preliminary design ongoing (1/19)
                             Preliminary design ongoing (2/19)
                             Preliminary design ongoing (3/19)
                             Preliminary design ongoing (4/19)
                             Preliminary design ongoing (5/19)
Construction anticipated to begin Summer 2020
 

Westmoreland Rd. - Joint MCIP Project # 2 - Dallas County
Engineer: Freese and Nichols
Contractor: TBD
• Project:  Westmoreland Rd. (Belt Line Rd. – Parkerville Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Preliminary design ongoing (12/18)
                             Preliminary design ongoing (1/19)
                             Preliminary design ongoing (2/19)
                             Preliminary design ongoing (3/19)
                             Preliminary design ongoing (4/19)
                             Preliminary design ongoing (5/19)
Construction anticipated to begin Winter 2020
      
Whispering Oaks Drainage
* Engineer: Dallas County
* Contractor: TBD
* Project:
Protect city outfall structure from falling into the creek.
Project Status:  Final design in progress (12/18)
                              Final design in progress (1/19)
                              Final design in progress (2/19)
                              Final design in progress (3/19)
                              Final design in progress (4/19)
                              Final design in progress (5/19)
Construction anticipated to begin Summer 2019
    

2018 Renovation and Replacement Project - Phase 2
Hunters Creek Dr., Foxwood Dr., Prairie Creek Dr. and Shadywood Lane
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project:Included in the Capital Improvement Program is the annual reconstruction of residential and collector asphalt streets. The scope of work for this project will consist of the pulverization of the existing asphalt, cement stabilization of the base material to a depth
of 6", and the construction of a new 6" asphalt roadway. 

Project Status: 
Evaluating bids ongoing (12/18)
                             Evaluating bids ongoing (1/19)
                             Evaluating bids ongoing (2/19)
                             Construction Contract Awarded (3/19)
 
                             Contractor Mobilization (4/19)
                             Asphalt work ongoing 20% complete (5/19)
Construction anticipated to begin Spring 2019